Advertisement Synopsis
Construction Engineering Services
August 1, 2003
STATE PROJECT NO. 742-26-0046 [Construction Inspection Services]
FEDERAL AID PROJECT NO. STP-2602(500)
VETERANS BOULEVARD OVERLAY
SUBURBAN CANAL TO BONNABEL CANAL OVERLAY
(PHASE I)
JEFFERSON PARISH
Under Authority granted by Title 48 of Louisiana Revised Statues, the Louisiana Department of Transportation and Development (DOTD) hereby issues a request for Qualification Statements (RFQ) on Standard Form 24-102 (SF 24-102), “Professional Engineering and Related Services”, revised January 2003, from Consulting Firms (Consultant) interested in providing construction engineering and inspection services to relative to the captioned project. One Prime-Consultant/Sub-Consultant(s) (Consultant/Team) will be selected for this contract. A map of the project limits for the proposed work is available upon request.
Project Manager
– The Project Manager will be Mr. Bruce Perdue, he may be reached at (504) 465-3473.
PROJECT DESCRIPTION
This is an Urban Systems project. The Consultant/Team will be required to provide construction contract administration and construction inspection services. The contract will be between the Consultant and Jefferson Parish. It will be monitored by Jefferson Parish, DOTD and the Federal Highway Administration (FHWA).
SCOPE OF SERVICES
The selected Consultant/Team will provide construction contract administration and construction inspection services required to reconstruct Veterans Boulevard from the Suburban Canal to the Bonnabel Canal. The construction project also includes drainage structures, cold planning asphaltic concrete, superpave asphaltic concrete, and pavement marking and related work. The services will be performed in accordance with DOTD’s latest specifications.
I. Mandated Construction Requirements:
1. Coordinate with DOTD District personnel to schedule and attend the Pre-construction Meeting. Consultant will be required to conduct the meeting.
2. Maintain all construction field records; make daily entries in the project diary to indicate the Consultant’s personnel and Contractor’s personnel present on the job site, the Contractor’s personnel and equipment being utilized on the project, the work being accepted, the acceptability of traffic control, and the charging of contract time.
3. Coordinate with the Parish Engineer/Representative for all relocations/adjustments of utility facilities for the construction of work site.
4. Provide all necessary equipment to perform the required field-testing for quality assurance in accordance with the latest DOTD Materials Sampling Manual and Testing Procedures Manual.
5. Submit all sampled materials to be tested by DOTD District 02 Testing Laboratory, in accordance with the Materials Sampling Manual and the Matt System Field Handbook.
6. Inspect the contractor’s construction operations (daily) to ensure that all work is performed in accordance with the specified plans and specifications.
7. Keep clear and concise records of the contractual operations, prepare monthly pay estimates, and make monthly progress reports in conformance with DOTD requirements. Inspection of construction will not include shop and mill inspections and their approval.
8. Prepare final estimate packages, including Form 2059 – “Summary of Test Results” in conformance with DOTD requirements.
9. Review all form work drawings and submit to DOTD for further handling, review, and distribution.
10. Coordinate all construction activities between the Consultant, the FHWA and an assigned representative of the DOTD. All work standards, methods of reporting, and documentation of pay quantities will be in accordance with the policies and procedures of the DOTD. All partial and final construction estimates, and other information must be submitted on forms approved by the DOTD.
11. The Consultant will be available for conferences, visits to jobsites, and/or inspections by DOTD authorized representatives.
12. The Consultant will be required to submit “As-Built” plans with the final estimate. “As-Built” plans are to reflect all changes made from the original plans. All changes to the plans are to be made using a 746-1/2 Tuscan red pencil.
II. Additional Consultant/Team Services Required:
1. When it is stipulated by the Project Specifications, that approval by DOTD is required for material, equipment, and/or construction procedures, DOTD policies for obtaining such approval will be followed.
2. All construction inspection personnel utilized by the Consultant must meet and retain the same qualification and certification requirements as required of DOTD construction personnel.
3. The Consultant will perform all surveying services when required. The Contractor will perform construction layout, and the Consultant will perform any necessary spot checks for verification.
4. Any proposed changes in plans or in the nature of the work will be pre-approved in writing by the DOTD, prior to the performance of stipulated work.
5. Plan changes throughout the life of the project will also have to be written by the Consultant and approved through the Department’s process.
6. The Consultant will monitor and document all construction claims, and provide recommendations on disposition of claims.
The services to be performed will be under the direct supervision of the DOTD. The services will be performed in accordance with the latest applicable DOTD Construction Administration Manual, Testing Procedures Manual, Materials Sampling Manual, Engineering Directives and Standards Manual (EDSM), and the latest version of the Louisiana Standard Specifications for Roads and Bridges with Supplemental Specifications and Special Provisions.
SERVICES TO BE PERFORMED BY THE DOTD
1. DOTD District 02 Laboratory in Jefferson Parish will perform laboratory tests and DOTD Materials Laboratory in Baton Rouge, Louisiana, will perform specialty tests using samples procured and submitted by the Consultant and/or his staff.
2. DOTD will provide project plans and contract proposal.
3. DOTD Structural/Marine Fabrication Engineer will perform all shop and fabrication inspection upon receipt of approved shop drawings.
ITEMS TO BE PROVIDED BY THE PARISH
1. Traffic Data
REFERENCES
All designs and engineering documents will meet the standard requirements as to format and content of the DOTD; and will be prepared in accordance with the latest applicable editions, supplements and revisions of the following:
1. AASHTO Standards, ASTM Standards or DOTD Test Procedures
2. DOTD Location and Survey Manual
3. DOTD Roadway Plan Preparation Manual
4. DOTD Hydraulics Manual
5. DOTD Standard Specifications for Roads and Bridges
6. Manual of Uniform Traffic Control Devices (Millennium Edition)
7. DOTD Traffic Signal Design Manual
8. National Environmental Policy Act (NEPA)
9. National Electric Safety Code
10. DOTD Environmental Impact Procedures (Vols. I-III)
11. Policy on Geometric Design of Highways and Streets
12. Construction Administration Manual
13. Materials Sampling Manual
14. DOTD Bridge Design Manual
15. Consultant Contract Services Manual
Copies of these documents will be made available through DOTD, General Files at (225) 379-1107.
COMPENSATION
Compensation to the Consultant for services rendered in connection with this contract will be made on the basis of a non-negotiated cost plus fixed fee of $14,415, with a maximum limitation of $144,206. Compensation for the project engineer will be subject to a maximum of 30% of the total project engineer hours, at the firm’s audited office overheard rate. The remaining 70% of the project engineer’s time and all inspectors will be calculated using the statewide field overhead rate.
CONTRACT TIME
The consultant will proceed with the services specified herein after the execution of this contract and upon written Notice-To-Proceed from the DOTD, and will be in effect for the duration of the construction period (80 working days), and the final estimate package, estimated to be 135 calendar days.
MINIMUM PERSONNEL REQUIREMENTS
The following requirements must be met at the time of submittal:
1. At least one Principal of the Prime Consultant must be a Registered Professional Civil Engineer in the State of Louisiana.
2. The Prime Consultant must employ on a full-time basis, one Registered Professional Civil Engineer, with at least five years experience in Road Construction, and a corresponding support staff.
3. In addition to the above requirements, the Prime Consultant must also employ on a full-time basis, or through the use of a Sub-Consultant(s), a minimum of two Certified Inspectors, including one Inspector with a minimum of five years experience in Road Construction. Inspectors are required to have a certification in Asphalt Plant and Asphalt Paving when inspecting corresponding activities.
EVALUATION CRITERIA
The general criteria to be used by DOTD (when applicable) in evaluating responses for the selection of a Consultant to perform these services are:
1. Consultant’s firm experience on similar projects, weighting factor of 3;
2. Consultant’s personnel experience on similar projects, weighting factor of 4;
3. Consultant’s firm size as related to the estimated project cost, weighting factor of 3;
4. Consultant’s past performance on similar DOTD projects, weighting factor of 6;
5. Consultant’s current work load, weighting factor of 5;
6. Location where the work will be performed, weighting factor of 6;
Sub-Consultants will also be evaluated as indicated in Items 1- 6. The evaluation will be by means of a point-based rating system. Each of the above criteria will receive a rating on a scale of 0-4. Then the rating will be multiplied by the corresponding weighting factor. The firm’s ratings in each category will then be added to arrive at the Consultant’s final rating.
If Sub-Consultants are used, each member of the Consultant/Team will be evaluated on their part of the contract proportional to the amount of their work. The individual team member ratings will then be added to arrive at the Consultant/Team rating. DOTD's Consultant Evaluation Committee will be responsible for performing the above described evaluation, and presenting a short list of the three (if three are qualified) highest rated Consultant/Team to the Secretary of the DOTD. The Secretary will make the final selection.
CONTRACT REQUIREMENTS
The selected Consultant will be required to execute the contract within 10 days after receipt of the contract.
INSURANCE
- During the term of this contract, the Consultant will carry professional liability insurance in the amount of $1,000,000. The Prime Consultant may require the Sub-consultant(s) to carry professional liability insurance. This insurance will be written on a “claims-made” basis. Prior to executing the contract, the Consultant will provide a Certificate of Insurance to DOTD showing evidence of such professional liability insurance.
AUDIT
- The selected Consultant/Team will allow the DOTD Audit Section to perform an annual overhead audit of their books, or provide an
independent
Certified Public Accountant (CPA) audited overhead rate. This rate must be developed using Federal Acquisition Regulations (FAR) and guidelines provided by the DOTD Audit Section. In addition, the Consultant/Team will submit semi-annual labor rate information, when requested by DOTD.
The selected Consultant/Team will maintain, an approved Project Cost System and segregate direct from indirect cost in their General Ledger. Pre-award and post audits, as well as interim audits, may be required. For audit purposes, the selected Consultant/Team will maintain accounting records for a minimum of five years after final contract payment.
Any Consultant currently under contract with the DOTD and who has not met all the audit requirements documented in the manual and/or notices posted on the DOTD Consultant Contract Services Website (
www.dotd.state.la.us
), will not be considered for this project.
SUBMITTAL REQUIREMENTS
Two copies of the SF 24-102 must be submitted to DOTD.
Inspector’s certification must be included in the SF 24-102.
All submittals must be in accordance with the requirements of this advertisement and the Consultant Contract Services Manual. Any Consultant/Team failing to submit any of the information required on the SF 24-102, or provide inaccurate information on the SF 24-102, will be considered non-responsive.
Any Sub-Consultants to be used, including Disadvantaged Business Enterprise (DBE) Sub-Consultants, in performance of this contract must also submit a SF 24-102, completely filled out and containing information pertinent to the work to be performed.
The Sub-Consultant’s SF 24-102 must be firmly bound to the Consultant’s SF 24-102. In Section 9, the Consultant’s SF 24-102 must describe the
work elements
to be performed by the Sub-Consultant(s), and state the approximate
percentage
of each work element to be subcontracted to each Sub-Consultant.
Name(s) of the Consultant/Team listed on the SF 24-102, must precisely match the name(s) filed with the Louisiana Secretary of State, Corporation Division, and the Louisiana State Board of Registration for Professional Engineers and Land Surveyors.
The SF 24-102 will be identified with State Project No.
742-26-0046
and will be submitted
prior to 2:00 p.m.
on
Monday, August 25, 2003
, by hand delivery or mail addressed to:
Department of Transportation and Development
Attn.: Dr. Babak Naghavi, P.E., P.H.
Consultant Contract Services Administrator
1201 Capitol Access Road,
Room 405-T
Baton Rouge, LA 70802-4438 or
Post Office Box 94245
Baton Rouge, Louisiana 70804-9245
Telephone: (225) 379-1989